Ascheduleis a timetable showing the forecast start and finish dates for activities or events within a project, programme or portfolio.
When a project manager has defined the scope of the project (the work that needs to be completed), understands quality requirements and risks, and has estimates of activity duration's in place, the next step is to put together a schedule (Starting out in project management, 3rd edition).
Definition fromAPM Body ofKnowledge7th edition
Time scheduling
Time schedulingis a collection of techniques used to develop and present schedules that show when work will be performed. The results of all these techniques are usually presented as activities or bars on a timeline, known as aGantt chart.
Understanding scheduling involves learning the terminology associated with critical path analysis – the main technique associated with scheduling Starting out in project management, 3rd edition.
Scheduling comes into project planningand there are principally two types of scheduling: critical pathandcritical chain.
Critical path
Thecritical pathapproach places emphasis on the activities in a project and understanding the shortest time to complete all activities in a logical order. It is a sequence of activities through a precedence network from start to finish, the sum of whose durations determines the overall duration.
Critical path analysisis an activity- based scheduling technique that determines the overall duration of the identified work based on estimates and logical dependencies.
It is the method of determining the critical path. Critical path analysis is almost exclusively performed using desktop scheduling software, although it is a key skill for project professionals to understand how this is done so they can verify that the project schedule is built on complete and defensible logic.
The purpose of a project manager understanding a project’s critical path(s) is to be able to focus effort in managing the activities that lie on it with the knowledge that if all of them complete on time, and if there is no slippage on other activities that exceeds thetotal float, the whole project will finish on time.
Critical chain
Thecritical chainis resource based approach to scheduling, useful when time is critical. It is derived from the critical path that protects critical chains of activities with buffers. The critical chain approach attempts to keep resources at a constant utilisation, avoiding common working practices such as:
- multitasking between activities;
- not starting planned work at the earliest start date and committing time until it is finished.
Both these practices result in any float (time contingency) in the estimate being lost to the overall project.
Watch: What is scheduling?
This video is hosted by a third party (YouTube.com), you cannot view this video content unless you accept marketing cookies. If the popup doesn't appear, please clear your browser cache and refresh the page.
Starting out in project management
Your essential guide to the basics of project management.Written for anyone new to projects or wishing to progress their career as a project professionalStarting Outcharts the journey of the APM project life cycle, from concept through to delivery and handover.
Buy from bookshop
Planning, scheduling, monitoring and control
Planning, Scheduling, Monitoring and Controlofferspractical guidance on all planning aspects of preparing to undertake a project, executing a project, controlling its delivery to budget, time and quality, and delivering it safely.
Buy from bookshop
Related reading
Knowing how to define and manage critical path is accepted as an essential skill for project managers.
Creating a project schedule is one of the most important tasks for us project managers at the start of any project... read more.
I'd like to introduce you to Critical Chain Project Management (CCPM). And if you think this is simply an alternative to critical path and earned-value, you might be interested to learn that it is much more than that... read more.
Every project should start with a clearly defined schedule showing when certain tasks start and finish, and when milestone stages and the final deliverable are due to be completed... read more.
APM Body of Knowledge 7th edition
The APM Body of Knowledge 7th edition is a foundational resource providing the concepts, functions and activities that make up professional project management. It reflects the developing profession, recognising project-based working at all levels, and across all sectors for influencers, decision makers, project professionals and their teams.
Buy from the bookshop
You may also be interested in
The APM Learning portal is an online resource which provides members with access to digital guides, modules and other digital learning resources as part of the membership benefit.
Browse our popular project management 'What is ...?' topics for definitions, quick insights, view related case studies, research, blogs and glossary.
Project – APM's official journal – is circulated quarterly for members only, and online for regularly updated news, blogs, opinions and insights for those in the project community.
The APM Community is our online community platform that connects our members faster and easier than ever before.